Three Clark County construction contracts now run along the stretch of the 215 Beltway closest to The Ridges, and each has its own finish date. The earliest is November 4, 2026, and it belongs to a trail undercrossing beneath Charleston Boulevard. The two projects drivers actually feel are both scheduled into 2028.
The order matters for this fall. The Summerlin Parkway interchange to the north is past its halfway mark and has moved most of its remaining work off the roadway. The Charleston-to-Far Hills widening to the south started in June and is now in the phase that puts cones on the ramps, on the side streets and at a Red Rock Casino driveway. For the next several months, most of the construction you drive through near The Ridges will be at the south end.
The projects share one stretch of freeway and run at the same time, but each finishes on a different date. Here is how the published dates line up:
| Project | Contract | Started | Estimated finish |
|---|---|---|---|
| Western Beltway Trail undercrossings at Charleston | $18,655,000 | November 3, 2025 | November 4, 2026 |
| 215 / Summerlin Parkway interchange | $130 million | Underway, 1,102-day schedule | Spring 2028 |
| 215 widening, Charleston Blvd to Far Hills Ave | $73.5 million | June 1, 2026 | January 21, 2028 |
Treat every date in that table as an estimate. The county's own paperwork disagrees with itself in places. The construction status list updated September 1 shows the trail finishing on August 29, 2026, while the newer construction notice moved that to November 4. For the widening, the status list gives January 21, 2028, and the county's 72-hour notice to neighbors says completion "by February of 2028." The trail notice says plainly that its cost and schedule figures are "the County's current best estimates and are subject to change."
Las Vegas Paving holds both the trail contract and the widening contract, so one contractor is working both projects at the 215 and Charleston at the same time.
The project closest to done is a pair of new segments on the Western Beltway Trail. One is a set of undercrossings west of the 215 beneath Charleston Boulevard. The other is an extension of the multi-use path west of the freeway between Fort Apache Road and Peace Way. The county's bid documents describe a 1,635-foot segment that joins the existing trail sections south of Peace Way and north of Fort Apache, plus ramp undercrossings connected by a path that runs under the Charleston bridge.
Today, a rider on the Beltway trail has to cross Charleston at the interchange on the surface. Clark County Commissioner Justin Jones put it this way in a September 28 FOX5 report:
"Once this project is officially open for cyclist, no longer will be the days where you have to cross 8 lanes of traffic along this stretch of Charleston Boulevard at the 215."
The same FOX5 piece notes that critics call the $18.6 million project unnecessary because the signalized crosswalks at Fort Apache, Peace Way and Charleston already exist.
The Red Rock Legacy Trail is a separate project. Its first mile, a paved out-and-back path along westbound Charleston past Sky Vista Drive, opened April 28, 2026, according to 8 News Now. No county document we found says the new Beltway undercrossing physically connects to the Legacy Trail. Until the county publishes a route that shows one, plan them as two separate rides.
The Summerlin Parkway interchange is the older and larger project. In the Review-Journal's Road Warrior column on September 28, project manager Dan Erickson said about 58 percent of the work had been billed by the end of August, slightly ahead of pace. The scope includes rebuilt ramps, a new flyover from the 215 southbound to the Parkway eastbound, five new vehicle bridges and three pedestrian trail bridges. All but one vehicle bridge is finished, and the last is due by the end of the year.
What matters most for drivers is Erickson's description of the work that remains:
"This project shouldn't have any closures coming up anytime soon. The major portion of the work is the walls and bridge, and that is all outside of traffic."
The next visible milestone, he said, is traffic moving onto the new Summerlin Parkway westbound ramp to the 215 northbound, passing under the new pedestrian bridge at the northeast corner, "maybe November or December." The paths leading to the finished pedestrian and bike bridges will stay closed until close to the end of the project, because there is "still a lot of dirt to move."
Some lane work is still scheduled near The Ridges. The column listed work through October 23 on the 215 in both directions between Far Hills Avenue and Lake Mead Boulevard, and on the northbound off-ramps to Far Hills and to Summerlin Parkway. Erickson pointed to one place where congestion keeps building: the southbound climb from Cheyenne toward Lake Mead, where concrete trucks "can only go up 10 mph up the hill."
The Charleston-to-Far Hills widening is moving the other way. Las Vegas Paving began work June 1 along Hughes Park Drive East and Summerlin Centre Drive. The county's notice for October 11 through 24 shows what that looks like at street level:
That notice covers two weeks of a project the county has scheduled for 600 days. When the Review-Journal reported the award in March, the plan was a 540-day schedule, so the expected finish has already moved later. The county's trail notice says neighbors directly affected by construction get notices 72 hours ahead, and Clark County Public Works takes questions at (702) 455-6000 or [email protected]. Expect new two-week notices with new configurations from here on, and check each one before assuming the Hughes Park Drive layout is the same as last time.
The finished widening changes more than lane count. According to the Review-Journal's March 23 report on the award, the project adds one lane in each direction between Charleston and Far Hills and builds a braided ramp from the 215 northbound to Charleston that crosses over Hughes Park Drive East. Clark County principal civil engineer Rahel Shibeshi told the paper that the new ramps will let drivers on Summerlin Centre Drive get on the freeway directly without using Charleston, and let drivers leaving the 215 reach Charleston directly.
That last change affects the side-street routes many drivers use now. Summerlin Centre Drive and Hughes Park Drive are the streets carrying the narrowed lanes and turn pockets during construction, and they are the same streets the finished ramps are designed to connect straight to the freeway.
New places keep opening in the meantime. Finney's Crafthouse opened September 21 at 10955 Oval Park Drive in Downtown Summerlin, according to Eater Vegas. A little farther east, The Resort at Summerlin opened its expanded casino floor and new Elyx Bar on October 6 at 221 North Rampart Boulevard.
For drivers, the near-term schedule comes down to a few dates. The Parkway ramp could shift to its final alignment in November or December. The north end's last vehicle bridge is due by year's end. On the south end, the widening is scheduled to keep working around Hughes Park Drive and Summerlin Centre Drive until early 2028. The Charleston undercrossing for trail users is the one item on the corridor still dated for this year, at November 4.
Construction on this scale changes how a home's location reads to buyers, and the same address can look different depending on whether it goes to market before or after these ramps open. If you are thinking about a sale or purchase in The Ridges and want to know how these timelines fit your own plans, Gianni Sammarco can walk you through it. Request a private market consultation and valuation.
Buyer Guides, Market Insights, Community Comparisons
From Summerlin to Henderson, a $5 million budget delivers dramatically different homes, views, homesites and lifestyles. Here's how the city's leading luxury communiti… Read more
Community Comparisons, Luxury Communities
Two of Henderson's most prestigious hillside communities offer extraordinary custom estates, panoramic Las Vegas views and guard-gated privacy. The differences in arch… Read more
Luxury Communities, Buyer Guides
Canyon Fairways Summerlin | Luxury Home Buyer's Guide
Luxury Communities, Buyer Guides
The Hollywood Hills of Las Vegas: Discover extraordinary Strip views, custom architecture, DragonRidge Country Club and the details that matter when purchasing a multi… Read more
Gianni looks forward to providing you a unique boutique memorable real estate experience from start to finish. Contact Gianni today!